KUALA LUMPUR — Kuala Lumpur City Hall’s (DBKL) flood mitigation plans include building six more holding ponds, in addition to the six currently in the works, ahead of anticipated heavy rainfall from a Super El Niño season.
KL Mayor Datuk Seri Fadlun Mak Ujud said nine on-site detention ponds (OSD) had already been completed with six underway. The additional six are projects slated for next year.
These ponds function as temporary rainwater storage areas before controlled release into drainage systems.
Fadlun said DBKL is also monitoring more than 65 privately developed ponds which can function as flood retention areas, in addition to completing a 1.3km flood barrier.
Other works done on a regular basis include maintenance on drainage systems, rivers and retention ponds quarterly, instead of twice a year previously.
Frequency of maintenance works will be increased during the monsoon season and be done every two months to clear sediment and maximise water flow, he added.
Additionally, modifications will be done to roadside drainage inlets to improve rainwater flow into the drainage network.
Fadlun said DBKL had allocated RM27 million for next year to continue efforts to reduce the number of flash flood hotspots to 10 or fewer.
To date, DBKL’s mitigation efforts had reduced the number of flood hotspots from 31 in 2022 to 14 this year.
Other measures include deploying 180-horsepower pumps at 10 low-lying areas to pump excess water into rivers.
Fadlun who was speaking at a press conference with Prime Minister’s Department (Federal Territories) Hannah Yeoh, said DBKL had also activated an operations room to monitor weather conditions.
The operations room will also obtain forecasts one to two hours in advance, coordinate response efforts and issue early warnings to residents in flood-prone areas.
Meanwhile, Yeoh said DBKL has been told to present its flash flood mitigation plans for the capital city to Prime Minister Datuk Seri Anwar Ibrahim ahead of the Northeast Monsoon and a possible Super El Niño phenomenon next year.
All DBKL branch offices in Kuala Lumpur’s parliamentary constituencies have also been told to provide real-time reports to the mayor whenever it rains, enabling immediate coordinated action.
She said two task forces were also focusing on enhancing flood mitigation efforts and turning open spaces into water-absorbing areas in line with the sponge city concept.
“In cities, floods can result in extensive damage to property and put lives at risk. Therefore, our efforts are coordinated and carried out regularly, not just when the Northeast Monsoon is imminent,” she said at the press conference today. – November 16, 2026