KUALA LUMPUR – Kuala Lumpur City Hall (DBKL) has reduced the number of flash flood hotspots in the capital from 31 in 2022 to 14 this year, with a further reduction to 10 targeted by the end of the year.
Minister in the Prime Minister’s Department (Federal Territories) Hannah Yeoh said the progress followed a directive by Prime Minister Datuk Seri Anwar Ibrahim for DBKL to prioritise flood mitigation through closer cooperation with the Department of Irrigation and Drainage (DID), while reviewing and adopting best practices in urban flood management, Bernama reported.
She said all DBKL branch offices across Kuala Lumpur’s parliamentary constituencies had been instructed to provide real-time updates to the mayor whenever rainfall occurred, allowing agencies to coordinate their responses promptly.
Two task forces have also been established to strengthen flood mitigation efforts and identify opportunities to transform open spaces into water-absorbing areas under the sponge city concept.
“In cities, floods can result in extensive damage to property and put lives at risk. Therefore, our efforts are coordinated and carried out regularly, not just when the Northeast Monsoon is imminent,” she said at a press conference after the Federal Territories State Disaster Management Committee meeting here today.
Hannah said 4,162 personnel from various Federal Territories agencies were on standby to respond to emergencies, supported by 139 lorries, 60 boats and 144 four-wheel-drive vehicles.
A total of 120 temporary relief centres have also been prepared, with the capacity to shelter up to 31,000 flood victims at any one time.
Meanwhile, Kuala Lumpur Mayor Datuk Fadlun Mak Ujud said DBKL had allocated RM27 million for next year to sustain its mitigation programmes and bring the number of flash flood hotspots down to 10 or fewer.
He said maintenance work on drainage systems, rivers and retention ponds was now conducted quarterly, compared with twice a year previously.
During the monsoon season, the frequency would be increased to once every two months to remove sediment build-up and ensure water could flow freely.
Seven contractors have been appointed to maintain drainage systems, while another 12 are responsible for maintaining retention ponds, he added.
Fadlun said DBKL would also modify roadside drainage inlets to improve the flow of rainwater into the city’s drainage network.
In addition, 180-horsepower pumps have been installed at 10 low-lying locations to channel excess water into rivers.
He said DBKL had completed nine on-site detention (OSD) ponds, with six more under construction and another six planned for 2027. The authority is also monitoring more than 65 privately developed ponds and has completed a 1.3km flood barrier.
DBKL has also activated an operations room to monitor weather conditions, obtain forecasts one to two hours ahead, coordinate emergency responses and issue early warnings to residents in flood-prone areas. – November 16, 2026