Nearly RM4 billion later, the River of Life is only 81% complete

Despite the cost and the project starting in 2018, it is not likely to be finished this year

9:10 PM MYT

 

KUALA LUMPUR – The River of Life (RoL) project is only 81% completed since its launch in 2018, after government expenditures of RM3.915 billion.

Minister in the Prime Minister’s Department (Federal Territories) Dr Zaliha Mustafa (Sekijang-PH) told the Dewan Rakyat that even though the RM4.363 billion project is not fully completed, Sg Klang and Sg Gombak are seen as waterfront icons with substantial economic value.

“This progress is evident through the accolades received,” she said when winding-up the debate on the 2024 Auditor-General’s Report 2/2024.

The report previously highlighted that the project, which is the most costly ever undertaken in Malaysia in a complex urban area, might not meet its scheduled completion this year.

As of July 2023, 12 projects remained in the pre-implementation stage, eight were under implementation, and contractors had not been appointed for two projects following termination of previous contracts.

Furthermore, the objectives of the RoL initiative remain partially unmet, specifically in achieving the goal of enhancing water quality in the river to Class IIB standards, suitable for recreational activities involving direct contact with the water. 

Additionally, beautification efforts along 2.2km of Sg Gombak have not taken place. – July 10, 2024

Topics

 

Popular

Duck and cover? FashionValet bought Vivy’s 30 Maple for RM95 mil in 2018

Purchase of Duck's holding company which appears to be owned wholly by Datin Vivy Yusof and husband Datuk Fadzarudin Shah Anuar was made same year GLICs invested RM47 mil

Thai oil giant pulls plug on Lang Lebah as Petronas-Petros feud looms large

Once dubbed Malaysia’s ‘project of the year’, Sarawak offshore project now faces an uncertain future amid budget blowouts and state-federal oil disputes with US$1 billion cost overrun

Six foreign players max on matchday under new MFL rule

Set to start in 2025-2026 M-League season, new quota reflects MFL’s commitment to strengthening national squad, ensuring clubs spend within their means

Related