First phase of ECRL track installation ahead of schedule: Malaysia Rail Link

ECRL track installation work has now entered its second phase, from Kuantan port to Maran

11:55 AM MYT

 

KUANTAN – The track installation for the first phase of the East Coast Rail Link (ECRL) project, spanning from Kuantan Port City (KPC), Pahang, to Dungun, Terengganu, covering a distance of 92 km, has been accomplished a month ahead of the projected schedule.

Malaysia Rail Link Sdn Bhd (MRL) chief executive officer, Datuk Seri Darwis Abdul Razak, attributed the achievement to the innovative “CCPG-500A” track laying machine, marking a pioneering advancement in the nation’s rail sector.

“On average, we managed to lay 1.5 km to 2 km of tracks per day, completing the KPC to Dungun stretch by the end of February, enabling full operation to commence at the beginning of March this year,” he informed the media.

He was speaking during the ECRL project iftar ceremony held here last night, attended by state exco, Razali Kassim, representing the Pahang Menteri Besar.

He stated that the ECRL track installation work has now entered its second phase since March 9, covering a mainline stretch of about 90 km from KPC to Maran, Pahang.

Overall, the ECRL route spanning 258 km in Pahang involves the construction of seven stations, including Cherating and KotaSAS for passengers only, while KPC, Paya Besar, Maran, Temerloh, and Bentong stations are combined passenger and cargo stations. – March 20, 2024

Topics

 

Popular

Petronas staff to be shown the door to make up losses from Petros deal?

Source claims national O&G firm is expected to see 30% revenue loss once agreed formula for natural gas distribution in Sarawak is implemented

Cleared for layoffs? AirAsia to retrench 20% of workforce in major cost-cutting move

This allegedly involves cabin services, cargo and logistics, engineering and maintenance, as well as the commercial division, according to Scoop’s source

No, Malays could not fly: Scholars call out pseudohistory

UPSI and DBP academics urge discipline in handling history after Prof Solehah’s claims of Malays teaching China ‘flying kung fu’

Related